My other request:
I have problems to see how much time will all the tasks last for today and the other days. This is critical to keep the schedule realistic while recheduling my tasks.
I have to set "filter by due date" (in the future: "filter by from date" - see my previous post) to enter the date and then I have it - the "estimated time" summary shows the overall time. But let's switch to see the overall time for some other days - it requires much too many clicks.
Possible solutions:
1) In the group header (or footer), add the summary for estimated time. I'll then group by due date / from date and see the sums more easily
OR
2) While filtering by due date, left / right arrow should go to the previous / next day. THe overall time for each day is already visible in the "estimated time" summary.
All the best,
Grzegorz
I have problems to see how much time will all the tasks last for today and the other days. This is critical to keep the schedule realistic while recheduling my tasks.
I have to set "filter by due date" (in the future: "filter by from date" - see my previous post) to enter the date and then I have it - the "estimated time" summary shows the overall time. But let's switch to see the overall time for some other days - it requires much too many clicks.
Possible solutions:
1) In the group header (or footer), add the summary for estimated time. I'll then group by due date / from date and see the sums more easily
OR
2) While filtering by due date, left / right arrow should go to the previous / next day. THe overall time for each day is already visible in the "estimated time" summary.
All the best,
Grzegorz