Dear Jim,
It's a pity, but at the moment there isn't a possibility to print the strikeout line on completed tasks.
You can set filters on completed and uncompleted tasks, when you set filters on these tasks, you can shift between filters by one click and print out the list of completed or the list of uncompleted tasks.
If you want to see only completed tasks on your task list, please do the following:
1. In "Filters Bar" choose "completed" in "Completion" field.
2. Click on "Save filter as.." button.
3. Enter filter preset name. (for example: completed tasks)
4. Click Ok.
If you want to see only uncompleted tasks on your task list, please do the
following:
1. In "Filters Bar" choose "uncompleted" in "Completion" field.
2. Click on "Save filter as.." button.
3. Enter filter preset name. (for example: uncompleted tasks)
4. Click Ok.